Exclusive-Boeing delays suppliers’ 737 MAX output goal by 6 months, sources say By Reuters


By Allison Lampert

(Reuters) – Boeing (NYSE:) Co has told suppliers it is delaying a key production milestone for its 737 MAX by six months, three industry sources said, in a sign the planemaker is struggling to boost production of its best-selling jet.

Boeing’s latest 737 supplier master schedule communicated to the industry calls for MAX output to reach 42 a month in March 2025, compared with a previous target of September 2024, the sources told Reuters.

Boeing has been struggling to recover production of its top single-aisle passenger plane due to additional safety and regulatory checks since a door panel dramatically flew off a 737 MAX jet in midair in January.

While the so-called master schedule is a demand signal, it is not an official production target. Boeing has not changed its official plane production target, which calls for 38 MAX jets a month by the end of 2024, up from roughly 25 jets a month in July.

When asked about the master schedule, a Boeing spokesperson directed Reuters to second quarter comments made by CFO Brian West in late July.

“On the master schedule, we continue to make adjustments as needed and manage supplier by supplier based on inventory levels,” West said. “Our objective remains to keep the supply chain paced ahead of final assembly to support stability.”

In an effort to align with Boeing’s lower production, supplier Spirit AeroSystems (NYSE:) in August temporarily lowered its monthly output of fuselages for the 737 MAX to 21 a month from 31, reducing demand for parts from its own supply chain, a senior industry source told Reuters.

Spirit AeroSystems spokesperson Joe Buccino said “we make adjustments of delivery and production rates with our suppliers in accordance with our supplier agreements.”



Source link

admin2

Share
Published by
admin2

Recent Posts

Bitcoin, Ethereum, Solana, BNB, & Hyperliquid: What Sets Them Apart

A framework for advisors comparing the major digital assets: Not all digital assets serve the…

1 hour ago

Hajj pilgrims arrive near Mecca ahead of Arafah Day | Religion News

NewsFeedMuslim pilgrims have begun arriving in Mina, near Mecca, ahead of the start of Arafah…

2 hours ago

Western premiers meet in Kananaskis under cloud of Alberta separatism

Premiers from Canada’s four western provinces and the three territories are meeting in Kananaskis Country,…

2 hours ago

On-X Casino бонусы и акции для новых и постоянных игроков.603 (2)

On-X Casino – бонусы и акции для новых и постоянных игроков ИГРАТЬ Содержимое Бонусы для…

2 hours ago

City of Vancouver unveils Human Rights Framework for FIFA World Cup – BC

The City of Vancouver has released its Human Rights Framework ahead of the FIFA World…

5 hours ago

Look to NOBL’s Growing Dividends in Volatile Rate Environment

Few market watchers would have predicted how much volatility markets would have seen at the…

6 hours ago